A 162-row dataset on 2 sheets, one answer cell, about 7 minutes. Graded in your browser: the value and the formula behind it, with feedback that names the fix.
How to solve it
- F2
=NETWORKDAYS(D2,E2,Holidays!$A$2:$A$13)
NETWORKDAYS(start, end, holidays) counts the days from the start date to the end date that are not Saturdays, Sundays or dates in the holidays list — both the start and the end day are included, so a ticket opened and closed on the same Tuesday counts as 1. The holidays argument is optional, but leaving it out silently over-counts every ticket that was open across a holiday; the list on its own sheet is what keeps the number honest. Locking that range as Holidays!$A$2:$A$13 lets the same formula fill down 150 rows.
Pitfall 1: forgetting the third argument — 122 rows still come out right, which is why the mistake survives review; the grader catches it because 28 rows differ. Pitfall 2: "inclusive" counting — NETWORKDAYS gives 1 for same-day resolution and 5 for Monday to Friday; if the SLA counts elapsed working days instead, subtract 1 (and guard same-day tickets with MAX(0,…)). Pitfall 3: a start date after the end date returns a negative count rather than an error; a text date in the holiday list is ignored silently, so keep that column as real dates. NETWORKDAYS.INTL(start,end,weekend,holidays) handles other weekends: 7 for Friday–Saturday, "0000011" as a 7-character string for a custom pattern; the plain function always assumes Saturday and Sunday. WORKDAY is the inverse: WORKDAY(D2,5,holidays) returns the due date five working days after the opening date — the usual way to compute an SLA deadline. Whole-column references (Holidays!A:A) work and survive additions to the list, but a named range (Formulas → Define Name → Holidays2026) reads better and is less error-prone than a hard-coded $A$2:$A$13.
Other ways that work
- =NETWORKDAYS.INTL(D2,E2,1,Holidays!$A$2:$A$13) — same result; 1 = Saturday/Sunday weekend
- =NETWORKDAYS(D2,E2,Holidays!A:A) — whole-column holiday reference, grows with the list
- =NETWORKDAYS(D2,E2,Holidays!$A$2:$A$13)-1 — elapsed working days, if your SLA excludes the opening day
Common mistakes
Omitting the holidays: =NETWORKDAYS(D2,E2) matches the answer for 122 tickets and is one or two days too high for the 28 tickets that were open across a company holiday.
How we grade
Any formula that produces the right result is accepted, unless the task names a function: then another function earns half credit. We compare values with a small tolerance and ignore case and spaces in text. A correct number typed by hand instead of a formula earns half credit. Multi-cell tasks earn full credit at 100% of cells, half credit from 50%. Where it matters, we also change an input cell on a copy of your sheet and check that your formula follows.
Answers computed with Excel 365 rules and checked in our grading engine on November 16, 2026. Author: GridBelt team.